|
|
|||
|
||||
OverviewNorthern Ireland has an ambitious target in place to have 40% of electricity consumed from renewable sources by 2020. To enable the achievement of the target there are around 31 wind farms totalling 552MW of large-scale generation and 250 small-scale generators totalling 65MW of electricity already connected. To achieve the target of 40% will require around 1,600MW of renewable capacity to be connected. There are currently 42 large-scale schemes in the pipeline at various stages of development. The current level of applications for small-scale renewables connections is extremely high. The high penetration of renewable electricity has already resulted in the distribution network having become saturated in some areas. As a result of grid congestion in some areas, connection costs are two to three times higher now than they were in 2012. Northern Ireland Electricity (NIE) accepts that, due to congestion on the grid, costs of grid connection in Northern Ireland are considerably higher than in Great Britain or the Republic of Ireland. The high number of applications for grid connections is also resulting in long delays for many developers. NIE concedes that there was a dip in service but states that increased staffing has resulted in significant improvements since last year. Full Product DetailsAuthor: Northern Ireland: Northern Ireland Assembly: Enterprise, Trade and Investment Committee , Patsy McGlonePublisher: TSO Imprint: TSO Volume: 196/11-16 ISBN: 9780339605459ISBN 10: 0339605456 Pages: 396 Publication Date: 11 December 2014 Audience: Professional and scholarly , Professional & Vocational Format: Paperback Publisher's Status: Active Availability: In stock We have confirmation that this item is in stock with the supplier. It will be ordered in for you and dispatched immediately. Table of ContentsReviewsAuthor InformationTab Content 6Author Website:Countries AvailableAll regions |